First Pour

We are building three buildings, House, Guest House, and Shop, because of the size of the project the concrete contractor has agreed that the two out buildings slabs will be poured, then the main house, then the walls of the out buildings, and finally the the walls of the house.

The day started early with the crews and pump trucks arriving at 5:30

38 meter pump truck.

The crews hung out till 6:50 when the first concrete trucks showed up. They had a crew of 17 workers and no one was ordering workers around, everyone knew what needed to be done next and just did it. One of the lead men did find a Supervisor.

Supervisor

By one thirty the crews were picking up and getting ready to call it a day.

Guest House.

So the guest house and shop foundations are curing and we will be starting to set the walls this week, and they should be pouring the foundation for the main house soon.